A roadmap for the Implementation of Annex 1 GMP.

The implementation of the new Annex 1 of the Good Manufacturing Practices (GMP) for the manufacture of sterile products in the European Union requires careful and detailed planning. The following is a sample roadmap that, with the necessary modifications for each case, can not only ensure a smooth transition and full compliance with the regulations, but also put them at the service of the business strategy as a further competitive advantage for the company:

Table of Contents

Phase 1: Initial Evaluation and Diagnosis

Objective: To conduct a comprehensive assessment of the current state of compliance against the new Annex 1 requirements.

  • Review of Annex 1: Internal review sessions with key teams (production, quality, maintenance, validation…) to ensure that all stakeholders understand the changes and requirements.
  • GAP Audit: Internal audit to identify gaps between current processes and the requirements of the new Annex 1. Classification of gaps according to their criticality (high, medium, low).
  • Identification of Critical Areas: Detection of priority areas that require immediate updating, such as environmental control, sterilization, personnel and material flow, and risk management.

Expected result: A detailed gap report and a preliminary corrective action plan.

Phase 2: Project Planning and Development

Objective: Define the necessary actions and develop a detailed implementation plan.

  • Creation of a Project Team:
    • Assignment of responsible for each key area (engineering, quality, operations, IT).
    • Definition of a project manager to centralize coordination.
  • Development of the Implementation Plan:
    • Definition of schedules, resources and budget.
    • Definition of monitoring KPIs to measure progress.
  • Development of updated procedures:
    • Review and update of standard operating procedures (SOPs) aligned with the new requirements of Annex 1.
    • Definition of additional controls for the validation of critical systems, such as HVAC, continuous monitoring systems, etc.
  • Equipment and Infrastructure Evaluation:
    • Assessment of whether the existing infrastructure meets the requirements of the new annex.
    • Planning for equipment upgrades or acquisitions, if necessary (e.g. SAS with VH₂O₂ biodecontamination, isolators or RABS).

Expected result: A comprehensive plan including timeline, budget and assigned personnel, as well as draft versions of the new procedures.

Phase 3: Implementation of Changes

Objective: To make the physical, operational and documentary changes required by Attachment 1.

  • Updating of Installations and Equipment:
    • Carrying out the necessary upgrades in the installations and in the critical environmental control systems, filtration systems, SAS or isolators.
    • Implementation of technologies to control viable and non-viable particles in real time.
  • Process Update:
    • Updating critical production processes, such as sterile filling lines, sterilization procedures and environmental monitoring.
    • Establish more robust control and monitoring measures for cross-contamination.
  • Education and Training:
    • Training of operators and quality personnel in the new policies and procedures.
    • Conduct audit simulations to ensure that all personnel are prepared for external audits.
  • Systems and Procedures Validation:
    • Revalidations of systems (e.g., HVAC, laminar flow, filtration) and processes ensuring the robustness of established controls.
    • Ensure full validation of any new equipment purchased during this phase.

Expected result: Full implementation of facility and procedural improvements, along with the necessary documentary validation.

Phase 4: Continuous Monitoring and Optimization

Objective: To ensure continuous compliance and seek opportunities for improvement.

  • Monitoring and Evaluation
  • External Audit and Certification
  • Continuous Optimization

Expected result: Sustained compliance with the new Annex 1, with an optimized system prepared for future regulatory audits.

Phase 5: Subsequent Evaluation and Innovation (Long Term)

Objective: To seek opportunities for innovation and optimization that exceed compliance.

  • Impact Assessment
  • Adoption of Technological Innovations
  • Preparation for Future Regulations

Expected outcome: An organization not only aligned with Annex 1 compliance, but also positioned to lead in sterile manufacturing innovation.

More current content...

Resistencia al fuego

Fire Resistance in Clean Rooms

Fire resistance in cleanrooms is essential to ensure safety and regulatory compliance in controlled environments.

In this article, we explore fireproofing materials, applicable regulations and construction solutions that ensure fire protection in critical spaces.

La Ciencia de las Salas Limpias

The Science of Cleanrooms

Do you remember those hours studying physics, chemistry or biology… and wondering what it would all be for someday?

In Iguña we were amused to remember it by reviewing the science behind something as technical (and as important) as cleanrooms…

45 Air Showers for a Battery Factory in France

A large battery factory in France has trusted us to equip its facilities with 30 high-efficiency air showers. In this article we show you how these solutions, tailor-made for people and materials, guarantee maximum decontamination with advanced technology, HEPA filtration and intelligent control.

Guía para la selección de aceros inoxidables 304, 316 y 316L en entornos críticos

Selection Guide for Stainless Steels 304, 316, and 316L in Critical Environments

Stainless steels 304, 316 and 316L are crucial in critical environments such as clean rooms. This article discusses their properties and corrosion resistance to guide selection according to application. Differences in composition, mechanical properties and ease of fabrication are explored. Discover how to choose the right stainless steel to ensure efficiency and durability in critical installations.